Sunday 23 February 2014

Site start

We had some issues with the permit and so the November 2013 start date was delayed. We finally 'went to site' on December 18th 2013. The excavation occurred fairly quickly however there's been no further progress due to the festive season. 





We now have a Site Supervisor (SS) and our Customer Support Coordinator has been replaced with a Building Support Coordinator (BSC).

The official completion date for the build is end of November 2014. Here's looking to moving in before Christmas!

We have enlisted the services of Urban Property Inspections. Hopefully we've made the right choice in building inspection company given our bad experience with choosing a demolisher. Hopefully the building inspection cost will be worth it!

No comments:

Post a Comment